All over Masury this spring and summer, FirstEnergy workers have been building temporary, plank roads to its tall, high-voltage transmission towers and using bucket trucks to replace insulators and crossarms on the towers, and replace some towers.
“Crews are updating aging equipment now to keep electricity flowing safely and reliably to hundreds of homes, schools and businesses across the region,” said spokeswoman Lauren Siburkis.
FirstEnergy is the parent company of Ohio Edison and Penn Power.
The Masury work is part of a larger project – the Masury-Maysville 69kv Re-Insulator Project – to replace 342 insulators, 50 transmission structures and 171 crossarms between Masury and Greenville, Pa., she said.
“Insulators are the stacked, spool-like pieces that connect power lines and their supporting structures, and they are essential for keeping electricity safely on the power line.” Siburkis said. “Over time, rain, ice, heat and strong winds can cause insulators to crack or wear down, increasing the risk of flickering lights or outages.”
Cross arms are the wooden beams that support power lines on utility poles, she said.
“Years of weather and constant pressure can raise the risk of equipment problems and power interruptions,” Siburkis said.
The improvements should make the power network more likely to keep electricity flowing, especially during storms, and improve safety, she said.
“Since 2020, FirstEnergy Transmission has reduced transmission outages in Ohio by 31 percent and by 33 percent in Pennsylvania – proof that the companies’ strategic infrastructure investments, like this work in the Mahoning and Shenango valleys, are making the grid more reliable for customers,” Siburkis said.
“This approximately $907,000 project is part of Energize365, FirstEnergy’s long-term investment program to modernize and strengthen the electric grid,” she said. “FirstEnergy plans to invest $36 billion between 2026 and 2030 to build a smarter, more resilient grid that meets the (needs) of communities across the service area.”
The Masury project began in April and is expected to be completed this fall, Siburkis said.